MAINTENANCE. A unit of the circulating fluidized bed coal-fired plant of Aboitiz Power Corporation undergoes a 10-day maintenance shutdown. (Photo courtesy of Black & Veatch)

MAINTENANCE. A unit of the circulating fluidized bed coal-fired plant of Aboitiz Power Corporation undergoes a 10-day maintenance shutdown. (Photo courtesy of Black & Veatch)

DAVAO CITY – The Davao Light and Power Company (Davao Light) advised its customers of a 10-day rotating power interruption which could last up to three hours due to a preventive maintenance shutdown of a coal-fired power plant.

A 150-megawatt unit of Therma South Inc.’s (TSI) coal-fired plant started its shutdown on Tuesday, February 16, and will end on February 26, DLPC said in a statement.

Davao Light holds a 50 MW contract from said generating facility, leaving the utility company with only 275 MW available power during the shutdown. Davao City’s average power demand hovers at 345 MW.

“The deficiency will now translate to two to three hours duration of rotating power interruptions,” Davao Light said.

Last January 23, the TSI’s 150 MW Unit 2 also underwent a corrective maintenance shutdown which lasted for seven days.

Sporadic outages

Davao Light explained that the power outages would come depending on the supply deficit on a certain hour in a day. This means that customers might find themselves experiencing brownouts without prior announcement from the company.

“The exact time when the power interruption will start in a given time frame still can not be determined as the power supply allocation varies every hour,” Davao Light said.

To minimize the chances of outages, DLPC said it will activate its Interruptible Load Program, a scheme where big establishments are required to independently generate their own power instead of relying from the grid during peak hours.

While the TSI coal-fired unit is shut down, DLPC said it will continue to take advantage of its contracts with other plants:

  • Therma Marine Inc. for 30 MW
  • Unit 1 of TSI coal-fired power plant for 50 MW
  • Hedcor Sibulan for 38 MW
  • Hedcor Talomo for 3 MW
  • Western Mindanao Power Corporation for 15 MW

Outages to alleviate Mindanao grid

The rotating outages are also being implemented to prevent the total shutdown of the Mindanao-grid, the company said.

For February 17, the National Grid Corporation of the Philippines projects that the Mindanao grid’s gross reserve will sink to a negative 15 MW.

In January, 18 towers belonging to the grid were attacked, with the latest incidents involving towers No. 19, 20, 21, 13, 25 and 50 of the Agus 2-Kibawe 138 KV transmission lines. Transmission tower No. 4 of the Baloi-Agus 2 138 KV transmission lines and the transmission tower No. 63 of Kabacan-Sultan Kudarat 138 KV transmission lines also experienced security attacks.

Such attacks, apart from the decreasing water level at the Lanao Lake which keeps the hydro power plants running, cause the grid’s capacity to fluctuate. (With additional reports from Mick Basa/davaotoday.com)